And yet, the RCN is getting butthurt because LCMMs are saying no to providing initial provisioning on AOPs 5 and 6 because they can't get both funding and procurement time to replace the items, so they need that for in service use. It's already been offloaded to AJISS.Initial provisioning is the responsibility of the project, not of NP.
But on occasion projects manage to escape their responsibilities...